The project's scope of work consist of a hydrocracker unit in Jazan Refinery located at Jazan Economic City, Saudi Arabia. The unit aims at maximizing distillate products (such as light and heavy naphtha, LPG and combined distillate). The construction of the hydrocracker unit (HCK) with associated facilities including two parallel trains with a capacity of 54,500 barrels per day (each) and a 99.5% conversion ratio.

Have been monitored manifacturing of following pumps:

  • #4 1ST STAGE REACTOR FEED/PUMP-6X15 DDHF /10 STG(HEP)
  • #6 2ND STAGE REACTOR FEED/PUMP-6X13 DDHF /11 STG
  • #4 HP LEAN AMINE/PUMP-6X13 DDHF /10 STG(NACE)
  • #6 1ST and 2ND TRAINS FEED/PUMP-6X13 DDHF

PROJECT INFO

Years: 2015-2016
Client: Saudi Aramco
Vendor: GE Nuovo Pignone - Bari (Italy)
Contractor: Tecnicas Reunidas
Object: Centrifugal pumps and skids

Jazan Refinery & Terminal - Hydrocracker Unit