HRSG Marghera Levante Brownfield project

SOMMARIO

The plant has an installed capacity of 780 MW and an energy efficiency of 63%, the highest output currently available, able to ensure a reduction of specific emissions of nitrogen oxides (NOx mg/kWh) by up to 70% and of carbon emissions (CO2 mg/kWh) by up to 30% compared to the current average of the Italian thermoelectric park, satisfying the equivalent annual needs of about 2,000,000 families.
Edison’s new 780 MW natural gas combined cycle of Marghera Levante consists of a 515 MW class 'H' turbine from Ansaldo Energia   – technologically ready for the use of up to 50% hydrogen mixed with natural gas – a heat recovery steam generator (HRSG) with a catalytic system for the reduction of nitrogen oxides (SCR) inside, and a 265 MW steam turbine (TVB).

INFO PROGETTO

Anni: 2020 - 2021

Monitoring on behalf of EDISON during HRSG fabrication at AC Boilers - Gioia del Colle (BA) plant

HRSG Marghera Levante Brownfield project

PROJECT RELATED